Problem Solver: Godwin Pump
Innovative pumping system diverts 75 mgd sewer flow during rehab project in Puerto Rico
Hydrogen sulfide (H2S) corrosion damage to wastewater treatment plant facilities often means time consuming and costly rehabilitation. This was the situation the Puerto Rico Aqueduct & Sewer Authority (PRASA) and the Puerto Rico Infrastructure Finance Authority (AFI) faced when H2S corrosion damage was discovered in both concrete piping and at two cast iron valve locations inside the Puerto Nuevo Wastewater Treatment plant.
To complicate matters further, the Puerto Nuevo plant is in the busy capital city of San Juan and handles 75 million gallons per day (mgd) of sewage.
Paramount to the successful completion of the $10 million rehab project to correct the H2S problems in the plant was ensuring that the sewage entering the facility could be safely diverted for a full four months while the repairs were being made.
In 1998, Godwin Pumps began working closely with AFI engineers to plan a pumping system to meet requirements for the bypass. AFI contacted Godwin Pumps because of Godwin’s reputation in the industry and its experience with this type and size job.
Godwin Pumps has supplied pumping equipment for bypasses as large as 150 mgd. However, Abbott commented, “We’ve been very successful with small bypass jobs as well — 1 mgd to 20 mgd.”
The bypass solution devised by Godwin Pumps to divert the flow entering the plant included 20 Godwin Dri-Prime DPC300 12-inch, diesel-driven pumps; 22,000 feet of 18-inch HDPE pipe; two fusion machines; and 10 specially designed discharge manifolds, each channeling two pumps into one main discharge line.
This 20-pump system proved to have the capacity needed to handle the daily average or peak flow and then some.
After weeks of preparation, the contractor, the local Godwin distributor — Puerto Rico Wire Products — and Godwin Pumps personnel put the bypass pumping system into operation. Over the next four months, while work was under way to address the maintenance problems in the plant, the Godwin team worked to oversee the system’s operation.
“This worked out really well,” said David Higgs, Godwin regional sales manager who served as project manager on this job. “Puerto Rico Wire’s involvement allowed Godwin Pumps’ U.S. crews to work with Bermudez & Longo’s project engineer Manuel Pelayo to get the system up and running. At that point, Puerto Rico Wire was able to take over and handle weekly routine maintenance.”
Higgs added, “It was a perfect example of international teamwork between all three organizations involved. The result was a successful design of a complex system.”
Leave A Comment